CHEQUERED PLATE

Chequered plates are same as plates, However small projection of same steel as per picture will be there.The small projection is kept for skid resistance and it will be used for walk way platforms.

Generally chequered plates are designated as Cheqd.PL -A o/p X Length X Width
Example: Cheqd PL-6 o/p X 1150 X 750

The term o/p means "over plate" or "over plain". It means thickness of the plate is excluding the chequer

The weight of chequred plate is higher than plane plate considering the  projections (Chequers).

Total weight: length (m) x width (m) x thickness (mm) x 7.85 + extra weight = kg/plate

Generally the extra weight will be 6.1Kg approximately. However the following table shows the weight of chequerd plates











Please note that sectional properties of the chequered plate while designing for bending and deflection,are based on the plain thickness of the plate, excluding thickness of the chequer.

Have a nice day
Related Posts Plugin for WordPress, Blogger...

Labels

Abbreviations (27) ABW (1) AC (2) Acre (2) Admixture (3) Alloy Steel (1) Analysis (1) ANSI (1) Anti friction bearing (2) Apothecaries Mass (1) Arc welding (1) Avoirdupois Mass (1) AWG (4) AWS (4) BCR 295 (2) Beam (22) Bearings (5) Blasting & Painting (8) Blogoversary (4) Bolt (8) CAR A/C (1) Cartoon (2) Cement (1) Cent (2) CHANNEL (8) Chequered Plate (1) Chinese (4) Civil (7) Classification (3) Cleaning (4) Cold Rolled Steel (2) Colour Code (1) Column Section (1) Computer (1) Concrete (4) Construction Industry (11) Conversion Table (4) Cooking (1) Crane Rail (2) Cylinders (1) Density (1) DFT (2) Drill bit (1) Drill gauge (1) Drilling (1) Dry Ice (1) EHS (1) Electrical (1) Electrode (1) Ellipcon Steel (1) Elliptical Hollow Section (1) EN 10083-3 (1) EN 10219 (1) Engineer Day (7) Engineering Miracle (2) Environment (1) Equipment (2) ESI (1) European Steel (3) Factory Act (1) fasteners (1) Fibre Rope (4) Fire (1) FLAT (3) floating crane (1) Flood (1) Foil (1) Formula (1) FRP (2) GAUGE (9) General (32) Greetings (9) H-beam (4) Handrail (1) Heavy Weight Beam (1) HeliArc (1) Helmet (2) HEXAGOAN (2) Hollow Rectangle (3) Hollow Square (5) Hollow Steel (10) Hot rolled Steel (30) HR & IR (2) HSFG (1) HSS (9) HT BOLT (1) I-Beam (4) Information (8) Informations (4) Introduce (4) IP (1) IPE (3) IS 1173 (5) IS 1363 (2) IS 1786 (1) IS 3443 (2) IS 4923 (2) IS 808 (15) IS:1732 (1) ISA (2) ISCR (1) ISHB (3) ISJB (4) ISJC (2) ISLB (3) ISLC (2) ISMB (4) ISMC (2) ISMCP (1) ISNT (2) ISSC (2) ISWB (3) JIS G3466 (1) Joints (1) Junior Beam (2) Junior Channel (3) Labour Law (5) Labour Welfare (3) Lamination (1) Land Measurement (2) Light Beam (2) Light Channel (3) LPG Cylinder (1) Man Day (1) Man Hour (1) Man Month (1) Mass (3) Measurement (3) mechanical (1) Metals (7) Mile Stone (2) Music Wire (4) MWG (6) Non-Metal (2) Numbers (3) OCTOGAN (1) Oil (1) Painting (6) Parallel Flange Channel (2) PFC (2) PIPE (4) Piping (4) Planning (2) Plastics (2) Plates (1) Pole (1) PPE (1) Precautions (3) Protection (1) Rain (1) Rebar (1) Reconciliation (2) Reinforcement Rod (1) Reinforcemnt Steel (1) Reo (1) Rigging (9) River on River (1) Rope (7) ROUND (2) RSJ (1) Safety (14) Scale (1) Self Explanatory (5) SEP (5) Serrated Flat (1) Sheet (3) Short cut key (1) Sling (1) Slit Tee (1) Specific Gravity (4) Spoon (1) SQUARE (2) SSPC (1) Steel (21) Steel Beam (7) Steel Section (6) Steel Section Type (5) Stick welding (1) Structural Steel (58) Surface Preparation (8) SWG (5) SWL (1) Technical (9) Tee Section (5) Thanks (7) TIG (1) TIG Welding (1) Tips (2) Tools & Tackles (2) Torque (6) Troy Mass (1) TUBE (2) Turnbuckle (1) UB (2) UC (2) Unit of Mass (1) UNIT WEIGHT (57) Universal Beam (1) universal Column (2) Useful Tips (2) Valve (1) Water (4) Weather (1) Weight (14) Welding (12) Wide Flange Beam (2) Wind (7) Wind Speed (4) Wire Rope (3) Wishes (19) WWD (1)

Contact Form

Name

Email *

Message *

Note

1) I have extracted the information from reference sources which may not be in accordance with the latest Standards - as identified.

2) The data’s are based on a review of various reference sources. For important work please check against quality information sources.

3) The Articles are no way connected to company of author belongs.

4) This Blog will not be liable for any, direct or indirect, consequential or incidental damages or loss arising out of the use of this information.

5) If you have any suggestions or feedback on how this blog can improve it for you, please feel free to e-mail me (engineerdiary@gmail.com) Self will try my best to keep up with it!

6) Paypal account of this site is engineerdiary@gmail.com

7) If your brand/company is keen to work with Engineer Diary for advertisement and sponsorship, you can drop us an email at engineerdiary@gmail.com

8) For More Disclaimer please refer Disclaimer Page