SWL for Mechanically Spliced Slings

Dear Readers,

During Rigging operations in construction we must know the SWL (Safe Working Load) of Rope and Tackles used. Some times we have to fabricate the sling from wire rope and suitably spliced. Permissible Load Lifting Capacity of Individual Slings fibre-core and mechanically spliced. Diameter of wire rope is in Inches and SWL is in MT
 
 
Size of Rope  = SWL
 
1). 1/2 "   =  1.196 MT
 
2). 5/8" = 2.133 MT
 
3). 3/4" = 2.683 MT
 
4). 1 " = 4.783 MT
 
5). 1 1/4" = 8.50 MT
 
6). 1 1/2" = 10.75 MT
 
7). 1 5/8" = 13.266MT
 
8). 1 3/4" = 15.383MT

 
 
 
 
It is always advised to take a load test by competent person / authorized agency before commencement of spliced sling in to operation/ Erection.
 
For More Details about SWL Click Here
For More Details about Steel Wire Rope Click Here 
Best Quote :
To be Successful in life, Forget the problems that you faced.. But, don't forget the lessons that you learnt from those problems. Have a Nice Day

0 comments:

Post a Comment

Related Posts Plugin for WordPress, Blogger...

Labels

Abbreviations (27) ABW (1) AC (2) Acre (2) Admixture (3) Alloy Steel (1) Analysis (1) ANSI (1) Anti friction bearing (2) Apothecaries Mass (1) Arc welding (1) Avoirdupois Mass (1) AWG (4) AWS (4) BCR 295 (2) Beam (22) Bearings (5) Blasting & Painting (8) Blogoversary (4) Bolt (8) CAR A/C (1) Cartoon (2) Cement (1) Cent (2) CHANNEL (8) Chequered Plate (1) Chinese (4) Civil (7) Classification (3) Cleaning (4) Cold Rolled Steel (2) Colour Code (1) Column Section (1) Computer (1) Concrete (4) Construction Industry (11) Conversion Table (4) Cooking (1) Crane Rail (2) Cylinders (1) Density (1) DFT (2) Drill bit (1) Drill gauge (1) Drilling (1) Dry Ice (1) EHS (1) Electrical (1) Electrode (1) Ellipcon Steel (1) Elliptical Hollow Section (1) EN 10083-3 (1) EN 10219 (1) Engineer Day (7) Engineering Miracle (2) Environment (1) Equipment (2) ESI (1) European Steel (3) Factory Act (1) fasteners (1) Fibre Rope (4) Fire (1) FLAT (3) floating crane (1) Flood (1) Foil (1) Formula (1) FRP (2) GAUGE (9) General (32) Greetings (9) H-beam (4) Handrail (1) Heavy Weight Beam (1) HeliArc (1) Helmet (2) HEXAGOAN (2) Hollow Rectangle (3) Hollow Square (5) Hollow Steel (10) Hot rolled Steel (30) HR & IR (2) HSFG (1) HSS (9) HT BOLT (1) I-Beam (4) Information (8) Informations (4) Introduce (4) IP (1) IPE (3) IS 1173 (5) IS 1363 (2) IS 1786 (1) IS 3443 (2) IS 4923 (2) IS 808 (15) IS:1732 (1) ISA (2) ISCR (1) ISHB (3) ISJB (4) ISJC (2) ISLB (3) ISLC (2) ISMB (4) ISMC (2) ISMCP (1) ISNT (2) ISSC (2) ISWB (3) JIS G3466 (1) Joints (1) Junior Beam (2) Junior Channel (3) Labour Law (5) Labour Welfare (3) Lamination (1) Land Measurement (2) Light Beam (2) Light Channel (3) LPG Cylinder (1) Man Day (1) Man Hour (1) Man Month (1) Mass (3) Measurement (3) mechanical (1) Metals (7) Mile Stone (2) Music Wire (4) MWG (6) Non-Metal (2) Numbers (3) OCTOGAN (1) Oil (1) Painting (6) Parallel Flange Channel (2) PFC (2) PIPE (4) Piping (4) Planning (2) Plastics (2) Plates (1) Pole (1) PPE (1) Precautions (3) Protection (1) Rain (1) Rebar (1) Reconciliation (2) Reinforcement Rod (1) Reinforcemnt Steel (1) Reo (1) Rigging (9) River on River (1) Rope (7) ROUND (2) RSJ (1) Safety (14) Scale (1) Self Explanatory (5) SEP (5) Serrated Flat (1) Sheet (3) Short cut key (1) Sling (1) Slit Tee (1) Specific Gravity (4) Spoon (1) SQUARE (2) SSPC (1) Steel (21) Steel Beam (7) Steel Section (6) Steel Section Type (5) Stick welding (1) Structural Steel (58) Surface Preparation (8) SWG (5) SWL (1) Technical (9) Tee Section (5) Thanks (7) TIG (1) TIG Welding (1) Tips (2) Tools & Tackles (2) Torque (6) Troy Mass (1) TUBE (2) Turnbuckle (1) UB (2) UC (2) Unit of Mass (1) UNIT WEIGHT (57) Universal Beam (1) universal Column (2) Useful Tips (2) Valve (1) Water (4) Weather (1) Weight (14) Welding (12) Wide Flange Beam (2) Wind (7) Wind Speed (4) Wire Rope (3) Wishes (19) WWD (1)

Contact Form

Name

Email *

Message *

Note

1) I have extracted the information from reference sources which may not be in accordance with the latest Standards - as identified.

2) The data’s are based on a review of various reference sources. For important work please check against quality information sources.

3) The Articles are no way connected to company of author belongs.

4) This Blog will not be liable for any, direct or indirect, consequential or incidental damages or loss arising out of the use of this information.

5) If you have any suggestions or feedback on how this blog can improve it for you, please feel free to e-mail me (engineerdiary@gmail.com) Self will try my best to keep up with it!

6) Paypal account of this site is engineerdiary@gmail.com

7) If your brand/company is keen to work with Engineer Diary for advertisement and sponsorship, you can drop us an email at engineerdiary@gmail.com

8) For More Disclaimer please refer Disclaimer Page